Job Costing โ Riverside Mixed-Use
Track budget vs actual by cost code, watch margin update live, and see work-in-progress against the contract value. Drag any actual to see profitability respond.
Contract value
$685,000
Budgeted cost
$528,000
Actual to date
$346,400
Budget variance
$181,600
Gross margin to date
$119,400 / 25.6%
Earned to date $465,800 at 68% complete
Cost Codes
01-100Labor โ Framing Crew
Budget $142,000$94,800
67%
02-200Materials โ Lumber & Steel
Budget $98,000$66,200
68%
03-300Equipment Rental
Budget $36,000$23,100
64%
04-400Subcontractors โ MEP
Budget $187,000$119,800
64%
05-500Permits & Compliance
Budget $21,000$13,900
66%
06-600Site Prep & Logistics
Budget $44,000$28,600
65%
Illustrative model for demonstration. A production build syncs actuals from your accounting system and field time entries, with WIP and cost-to-complete reporting per project.